ANALISIS KINERJA WAKTU DAN BIAYA PROYEK KONSTRUKSI DENGAN METODE EARNED VALUE ANALYSIS
DOI:
https://doi.org/10.36277/geoekonomi.v13i2.219Keywords:
time, cost, earned value analysis, scheduleAbstract
The International Airport Sultan Aji Muhammad Sulaiman (SAMS), Sepinggan Balikpapan is the gateway to East Kalimantan and is an airport with high aircraft movements every year. Periodic maintenance must be carried out to support airport performance. Runway surface overlay and paved shoulders is one of the works carried out for this purpose. In a construction project, good management is needed to control so that the project runs according to the planned time and cost. Earned Value Analysis (EVA) is one method that can be used to control projects. After analyzing using project data from week 1 to week 47, it is known that the costs incurred are greater than the budgeted value, this is indicated by the CPI value = 0.998. The implementation time is faster than the planned schedule, as seen in the SPI value of 1.142. The result of the final calculation of the project which indicates a loss and an estimated turnaround time of 65 weeks indicates a 4 week acceleration.
Downloads
References
Azizah, Siti Umi, Fakhrul Rozi Yamali, and Elvira Handayani. 2020. “Analisa Nilai Hasil Terhadap Waktu Pada Proyek Pembangunan Gedung Laboratorium FKIP Tahap IV (Lanjutan) Universitas Jambi.†Jurnal Talenta Sipil 3(2): 95.
Cipto, Rahajeng Cahyaning Putri. 2021. “Analisis Faktor-Faktor Yang Mempengaruhi Kinerja Pada Tenaga Kerja Bantuan (Honorer) Dinas Perhubungan Kota Balikpapan.†12(September 2021): 221–32.
Hasan, Famila. 2021. “Performance Analysis of Working Time And Cost of Rigid Arteries Using Earned Value Analysis ( EVA ) Method ( Case Study : Of the Construction Project of the Becakayu Toll Access Bridge on and off Ramp Jatiwaringin ).†3(5): 491–93.
Hendriyani, Irna, Andi Marini, and Nur Intan Putri. 2018. “Analisis SWOT Pemilihan Material Dinding Bata Merah Dan Bata Ringan Di Penajam Paser Utara.†Borneo Engineering : Jurnal Teknik Sipil 2(1): 22.
Juwari, Sudjinan, Ting Anita. 2021. “Pengelolaan Assets Perusahaan Dalam Optimalisasi Laba.†Geo Economi 12(1): 91–100.
Pratiwi, Reno et al. 2022. “Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off ( Tcto ) Pada Proyek Penambahan Bangunan Time And Cost Optimization Using The Time Cost Trade Off Method In The People ’ S Market Additional Building Project.†TRANSUKMA 4(2): 93–105.
Romadhona, Syahrur, Fredy Kurniawan, and Julistyana Tistogondo. 2021. “Project Scheduling Analysis Using the Precedence Diagram Method (PDM) Case Study: Surabaya’s City Outer East Ring Road Construction Project (Segment 1).†International Journal of Engineering, Science and Information Technology 1(2): 53–61.
Sari, Hikmah Maya, Irna Hendriyani, and Alifah Ersa Widyaningrum. 2021. “Earned Value Analysis Pada Proyek Pembangunan Gedung Arsip Kantor BPN: Earned Value Analysis of BPN Office Archives Building Projects.†Jurnal Ilmiah Teknik Sipil TRANSUKMA (Tanah Transportasi Struktur Manajemen Kontruksi) 3(2): 154–67. https://transukma.uniba-bpn.ac.id/index.php/transukma/article/view/84.
Sugianto, Agus, and Andi Marini Indriani. 2016. “Analisis Perbandingan Biaya Pekerjaan Rangka Atap Baja Ringan Dengan Rangka Atap Kayu.†2(1): 16–23.
Zega, A T. 2022. “Penerapan Dan Earned Value Analysis (EVA) Pada Proyek Pembangunan Gedung Di Tanah Merah Binjai.†Citra Sains Teknologi 1(2002): 120–27.
Downloads
Published
How to Cite
Issue
Section
License
You are free to:
Share - copy and redistribute the materials in any medium or format for any purpose, even for commercial purposes.
Adapt - compose, change and develop the material for any purpose, even for commercial purposes.
The licensor cannot revoke these freedoms as long as you follow the license terms.
With the following conditions:
Attribution - you must give appropriate credit, provide a link to the license, and indicate if changes have been made. You may do so in a reasonable manner, but not in any way that suggests that the licensor endorses you or your use.
No additional restrictions - You may not implement legal provisions or technological measures that legally restrict others from doing anything permitted by the license.
Notice:
You do not have to comply with the license for elements of the material that are in the public domain or where your use is permitted by an applicable exclusion or restriction.
No warranties are given. This license may not grant all the permissions necessary for your intended use. For example, other rights such as publicity, privacy, or moral rights may limit how you use the material.